In the Gypsum Wallboard Ceilings construction sequence, which step comes second?

Prepare for the NYSID Materials and Methods Exam 1. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Multiple Choice

In the Gypsum Wallboard Ceilings construction sequence, which step comes second?

Explanation:
The step being tested is about building the suspended ceiling grid in the correct order. After you establish the vertical support by attaching pencil rods to the deck (the redirection point that holds everything up), the next move is to create the horizontal frame that defines the ceiling plane. Attaching carrying channel angles to those pencil rods does exactly that: it turns vertical hangers into a workable grid. Once this horizontal frame is in place, you can install the 1.5 inch U-channel to form the main runners, and then the furring (hat) channels to complete the support for the gypsum board. Starting with the vertical rods ensures the grid has a stable, level reference before the horizontal members are added.

The step being tested is about building the suspended ceiling grid in the correct order. After you establish the vertical support by attaching pencil rods to the deck (the redirection point that holds everything up), the next move is to create the horizontal frame that defines the ceiling plane. Attaching carrying channel angles to those pencil rods does exactly that: it turns vertical hangers into a workable grid. Once this horizontal frame is in place, you can install the 1.5 inch U-channel to form the main runners, and then the furring (hat) channels to complete the support for the gypsum board. Starting with the vertical rods ensures the grid has a stable, level reference before the horizontal members are added.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy